Green Valley Road
Mixed-Use Path Project

Construction Schedule 

Phase 1-Airport Blvd to Pinto Lake City Park: July 15th-Mid-September, 2024-Airport Blvd to Amesti Rd has been paved-Amesti Rd to Pinto Lake City park construction of drainage and curb ramps completed 

Phase 2- Paulsen Road to Pinto Lake County Park: August 14th-November 6th, 2024-Base preparation complete, paving complete, drainage and landscape improvements on-going

Phase 3-Pinto Lake City Park to Paulsen Road: October 2nd, 2024-January 3rd, 2025- Base preparation complete, paving complete, drainage and landscape improvements on-going

Phase 4-Pinto Lake County Park to Mesa Verde Drive: November 21st, 2024-February 28th, 2025-Base preparation complete, paving complete, drainage and landscape improvements on-going

Project Striping will be completed near the end of the project

This schedule is approximate and is subject to change. 

Below is a 3 week schedule starting March 10, 2025

Amesti Road Striping Plan

This striping plan for the intersection of Amesti Road and Green Valley Road shows what the intersection will look like once the striping is complete. The county is aware that the current one lane configuration of the south bound lane of Amesti Road is inconvenient and appreciates your patience. Completion of the striping for the project is anticipated at the end of the project in February 2025.